EU satnav project ill-conceived: auditors court
BRUSSELS, June 29, 2009 (AFP) -

The EU's much delayed satellite navigation network project Galileo has been ill-prepared and badly managed, the European Court of Auditors charged Monday.

"The programme lacked a strong strategic sponsor and supervisor: the (European) Commission did not proactively direct the programme, leaving it without a helmsman," the auditors' court opined after carrying out an audit of the ill-starred project.

As well as the commission -- the EU's executive arm -- the 27 member states came into criticism for promoting their own industries first and foremost.

"Owing to their different programme expectations, member states intervened in the interest of their national industries and held up decisions. The compromises made led to implementation problems, delays and, in the end, to cost overruns," the official auditors declared.

The 30-satellite network is meant to challenge the dominance of the US-built Global Positioning System (GPS), which is widely used in navigation devices in vehicles and ships. The EU aims to have it up in space by 2013.

The EU has struggled to secure financing for the project's budget, originally 3.4 billion euros (5.4-billion dollars) -- and has had to release unused funds from the bloc's massive agricultural budget.

The audit examined the factors in the failure of the concession process and for delays and cost overruns of technological development.

It concluded that the original public-private partnership plan was "inadequately prepared and conceived" not to mention "unrealistic".

The Galileo Joint Undertaking -- a body set up in 2003 and scrapped in 2006 -- was given the task of supervising Galileo's technological development activities but "was seriously constrained by governance issues, an incomplete budget, delays and the industrial organisation of the development and validation phase," the report said.

If the Galileo project is to succeed, the European Commission "must considerably strengthen its management of the programmes," the Court of Auditors said.

"Finally, should the EU resolve to engage in other large infrastructure programmes, the commission must ensure it has access to the appropriate management tools," it added.

The report makes grim reading for the European Commission not least because the Galileo programme was the first of its kind.

"We acknowledge that there were delays and cost overruns," a European Commission spokesman said.

"In hindsight things could always be done better... but we are happy to accept the recommendations of the court in order to be able to get on with the project," he added.

While unable to quantify the cost or time overruns, he said the first operational satellites should be launched next year.

The auditors' report said that the stalling of negotiations with private sector companies in 2007 means "technological development has been set back five years".

While test satellites have been launched none of Galileo's 30 operational satellites have been put in space yet.

The project was the first close collaboration between the European Space Agency (ESA) and the commission on such a large space programme, the first industrial programme to be managed at European level and the first time the commission was to participate in a public private partnership scheme.

User avatar
CraigRat
850 or more found!!!
850 or more found!!!
Posts: 7015
Joined: 23 August 04 3:17 pm
Twitter: CraigRat
Facebook: http://facebook.com/CraigRat
Location: Launceston, TAS
Contact:

Post by CraigRat » 30 June 09 12:37 pm

Ahhh the E.U, nothing like 15+ countries with old rivalries trying to come up with an elegant solution :lol:

Methinks the Chinese will br the 1st to get their alternate system up.

User avatar
TeamAstro
5000 or more caches found
5000 or more caches found
Posts: 625
Joined: 01 April 04 10:57 pm
Location: Adelaide
Contact:

Post by TeamAstro » 30 June 09 11:06 pm

ELDO revisited?

ummm, clear skies, Astro. :roll:

User avatar
The Spindoctors
Posts: 1767
Joined: 08 October 03 8:00 pm
Location: Sydney
Contact:

Post by The Spindoctors » 30 June 09 11:25 pm

TeamAstro wrote:ELDO revisited?

ummm, clear skies, Astro. :roll:
Got to love the Germans and French working together, while the Brits whinge on the sidelines (while not giving any funding). You're right Astro, nothing changes.

At least they were consistent in using metric units. Don't mention the Mars '98 Orbiter mission out loud in NASA circles (one mile does not equal one kilometre).

It doesn't make sense to me to have too many competing systems. Russia have half a one, the Chinese have a few sats in orbit too.

ESA is better putting its money into servicing the ISS, especially given the Orion is on shaky ground. Not sure if I'm looking forward to the test Ares 1 launch in August.

Kerry
Posts: 224
Joined: 22 April 03 6:45 pm
Location: Australia

Post by Kerry » 01 July 09 6:57 pm

What's new? Been this way for the past 10 years.

Post Reply